Islanded simple-cycle

76 questions this plant already has.

You are not the designer. You audit the drawing, defend the field, and have to be useful at first fire. Start at Plant identity if you do not yet have the three facts that hang every other module.

Primer will not invent this plant’s megawatts, kV, or machine model. Shop-floor physics lives on trades.

Confidence discipline

Unverified on any plant of this type

Not answers. Things a primer must refuse to guess. Pull them from the named document.

  • Exact machine model, variant, and combustor type (DLN vs diffusion with diluent)

    Vendor submittal; mechanical equipment schedule

  • Any first-of-a-kind unit — rating, control platform, reference installation

    Vendor submittal; FOAK package

  • SCR presence, catalyst type, tempering / heat management

    Mechanical drawings, P&IDs, air permit

  • Aqueous ammonia concentration and PSM/RMP applicability

    Process piping section; ammonia skid submittal

  • Generator terminal voltage, step-up, distribution voltage levels

    Electrical one-lines

  • System grounding method (solid / LRG / HRG / ungrounded)

    One-lines and grounding study

  • Inlet cooling — whether installed, and of what type

    Mechanical drawings

  • Headline capacity: ISO, site, or net delivered

    Owner basis of design

  • Thrust restraint design authority

    Often absent — RFI, not a field guess

  • Pressure-class conflict between site-utility and fire protection

    Order of precedence, then RFI to EOR

  1. 06 questions

    Plant identity

    Islanded, behind-the-meter, computing load. Every unusual drawing traces to those three.

  2. 09 questions

    The machine

    Brayton cycle, back-work, derate, Wobbe, SCR on hot exhaust. A turbine is not 'a turbine.'

  3. 09 questions

    The island

    Frequency is shaft speed. Fault current decays. 51V, droop, black start, sync.

  4. 08 questions

    Piping and BOP

    Pipe class literacy, B31.1, WPS/PQR/WPQ, pickling, nozzle loads, hydro extent.

  5. 08 questions

    Civil and foundations

    Expansive clay, drilled piers, hot-weather concrete, PEMB setting-plan loop.

  6. 08 questions

    Controls and loops

    P&ID as a narrative. Loop check ≠ functional test ≠ logic test. Two overspeeds.

  7. 08 questions

    Construction execution

    IFC versus permit set. RFI as design-intent. Hold versus witness. Diagrammatic drawings.

  8. 08 questions

    Commissioning

    Area to system. Six milestones. Lube-oil flush as schedule risk. Real trips, not simulated.

  9. 06 questions

    Operations

    Part-load heat rate versus spinning reserve. Surge. Hours versus starts. Peak demand plus peak ambient.

  10. 06 questions

    Codes and permits

    B31.1 versus B31.3. NFPA 56 before gas. PSD/BACT. Aqueous ammonia thresholds. IEEE literacy.